A Beginner’s Guide to the Interconnection Queue

Shift Key with Robinson Meyer and Jesse Jenkins - Een podcast door Heatmap News - Woensdagen

Podcast artwork

Maybe you’ve never heard of it. Maybe you know it too well. But to a certain type of clean energy wonk, it amounts to perhaps the three most dreaded words in climate policy: the interconnection queue. The queue is the process by which utilities decide which wind and solar farms get to hook up to the power grid in the United States. Across much of the country, it has become so badly broken and clogged that it can take more than a decade for a given project to navigate. On this week’s episode of Shift Key, Jesse and Rob speak with two experts about how to understand — and how to fix — what is perhaps the biggest obstacle to deploying more renewables on the U.S. power grid. Tyler Norris is a doctoral student at Duke University’s Nicholas School of the Environment. Claire Wayner is a senior associate at RMI’s carbon-free electricity program, where she works on the clean and competitive grids team. Shift Key is hosted by Robinson Meyer, the founding executive editor of Heatmap, and Jesse Jenkins, a professor of energy systems engineering at Princeton University.Mentioned: Tyler’s study on “energy only” interconnection rulesHeatmap’s Matthew Zeitlin on the big problems with PJMFERC Order 2023Advanced Energy United’s report on unsnarling the gridSubscribe to Heatmap PlusRob’s downshift; Jesse’s upshift.--This episode of Shift Key is sponsored by …Watershed’s climate data engine helps companies measure and reduce their emissions, turning the data they already have into an audit-ready carbon footprint backed by the latest climate science. Get the sustainability data you need in weeks, not months. Learn more at watershed.com.As a global leader in PV and ESS solutions, Sungrow invests heavily in research and development, constantly pushing the boundaries of solar and battery inverter technology. Discover why Sungrow is the essential component of the clean energy transition by visiting sungrowpower.com.Antenna Group helps you connect with customers, policymakers, investors, and strategic partners to influence markets and accelerate adoption. Visit antennagroup.com to learn more.Music for Shift Key is by Adam Kromelow. Hosted on Acast. See acast.com/privacy for more information.

Visit the podcast's native language site